A track record
of success
Implementing successful PV projects requires a broad range of skills, resources, and personnel. The larger the project, the more weight each small decision carries for costs, quality, and construction time. Our extensive track record testifies to our ability to execute — quickly, and at scale.
While the CTIEC Group will further develop its solar park business in Europe continuously, CTF Solar itself will focus on the development of its CdTe technology for thin film solar panel production.
Wormit Farm
4.96 MWp
Fife, Scotland, UK
› AEG polycrystalline modules
› inverter: Huawei
› mounting structure: Heintzmann Industries
› 3-week construction time
› March 2016 grid connection
› construction finance: CTIEC/CTF Solar
› general EPC: CTF Solar
Lower Stanley Farm
4.93 MWp
Gloucestershire, UK
› AEG polycrystalline modules
› inverter: Huawei
› mounting structure: Heintzmann Industries
› 7-week construction time
› March 2016 grid connection
› construction finance: CTIEC/CTF Solar
› general EPC: CTF Solar
Stanton under Bardon Farm
3.66 MWp
Leicestershire, UK
› AEG polycrystalline modules
› inverter: Huawei
› mounting structure: Heintzmann Industries
› 3-week construction time
› March 2016 grid connection
› construction finance: CTIEC/CTF Solar
› general EPC: CTF Solar

Hayford Farm
9.8 MWp
Shrewsbury, UK
› 39,238 polycrystalline Jetion PV modules (250 Wp)
› 4 central inverter stations
› mono pile mounts
› 10-week construction time
› September 2014 grid connection
› construction finance: CTIEC
› general EPC: CTIEC / CTF Solar GmbH
Pentre Farm
6.1 MWp
Llanelli, UK
› 24,012 polycrystalline Jetion PV modules (255 Wp)
› 3 central inverter stations
› mono pile mounts
› 7-week construction time
› September 2014 grid connection
› construction finance: CTIEC
› general EPC: CTIEC / CTF Solar GmbH


Raventhorpe Farm
39.3 MWp
Scunthorpe, UK
› 153,617 polycrystalline Jetion PV modules (260 Wp)
› 17 central inverter stations
› mono pile and ballasted mounts
› 6-week construction time
› March 2015 grid connection
› construction finance: CTIEC
› general EPC: CTIEC / CTF Solar GmbH
Roanhead Farm
7.1 MWp
Barrow-in-Furness, UK
› 28,382 polycrystalline Jetion PV modules (255 Wp)
› 3 central inverter stations
› mono pile mounts
› 5-week construction time
› March 2015 grid connection
› construction finance: CTIEC
› general EPC: CTIEC / CTF Solar GmbH

Project location | Year | Project name | MWp |
---|---|---|---|
China | 2013 | Demonstration PV project in Bengbu Glass Industry Design and Research Institute Technology Center | 10,08 |
China | 2013 | CNBM New Energy Yuli Project | 20,00 |
Thailand | 2014 | Nongkee Ground PV Project | 12,50 |
Thailand | 2014 | Phachinburi Ground PV Project | 25,00 |
Thailand | 2014 | Prakhoncha Ground PV Project | 12,50 |
UK | 2014 | Kienetica Liannon Ground PV Project | 6,10 |
UK | 2014 | WSS HAYFORD Ground PV Project | 9,80 |
China | 2015 | CNBM project in Baode, Xinjiang | 20,00 |
China | 2015 | CNBM project in Keping, Xinjiang | 20,00 |
China | 2015 | Shangjian project in Yinjisha, Xinjiang | 20,00 |
China | 2015 | Tiemengguan Solar Power Plant | 2,00 |
China | 2015 | Triumph Huainan Heavy Industry Co., Ltd distributed Rooftop Plant | 16,00 |
Japan | 2015 | PV Plant in Chiba | 2,05 |
Japan | 2015 | PV Plant in Ōtawara, Tochigi | 0,95 |
UK | 2015 | Raventhorpe Farm Ground PV Project | 40,00 |
UK | 2015 | Roanhead Farm Ground PV Project | 7,10 |
USA | 2015 | Project in Maryland, USA | 7,34 |
UK | 2016 | Gretton, England, UK | 4,93 |
UK | 2016 | Shotwick Solar Power Plant | 70,00 |
UK | 2016 | Stanton under Bardon, England, UK | 3,66 |
UK | 2016 | Wormit, Scotland, UK | 4,96 |
UK | 2016 | Wroughton Afirfiedl Solar Power Plant | 60,00 |
China | under construction | CNBM(Hefei) New Energy Co.,Ltd distributed Rooftop Plant | 9,00 |
China | under construction | Organic Vegetable cultivation pv project in Baishiling, Yangxi |
30,00 |
China | under construction | Shangshantang Greenhouse pv project in Weihai (Phase 2) |
40,00 |
China | under construction | Zhonghe Groupe PV Project | 18,00 |
Japan | under construction | Solar power project in Kashima, Ibaraki | 1,98 |
Installed capacity in total (MWp) | 473,95 |